We are currently expanding our building  with an addition of approximately 6,000 square feet, adding multifunctional space, classrooms, updated kitchen, and additional bathrooms. The multifunctional space will serve our congregation as well as be a space that can be used for outreach and community engagement.

Progress Update

Concrete walks, patios, and ceiling grid went in, as well as ceiling duct work and electrical. The wood column enclosures were installed, the glass finished up and the final work on the roof top units was completed so all equipment on the roof is operational. Next week ceiling hook-ups continue, an “above ceiling” inspection will happen once electrical, mechanical and fire protection is complete, the wood columns stained, and the flooring installation will begin.

  